Craig J. Opperman P.E., Scioto County Engineer, announced the work schedule for the week of May 9, 2016
through May 13, 2016 for his office.
ROAD CLOSURE
Morris Lane – Blue Run Road (CR54) in Jefferson Township at the 2.97 mile marker will be closed Monday,
May 9th from 7:00 A.M. to 5:00 P.M. The location of the closure is between Blue Run Road and Blue Run
Township Road. County Engineer Craig Opperman’s crew will be installing a concrete pipe
Great Meadow Road (CR51) in Bloom Township at the 1.87 mile marker will be closed Monday, May 9th from
7:00 A.M. to 5:00 P.M. The location of the closure is between Martin Road and Webster Hope Road. County
Engineer’s crew will be installing a concrete pipe.
Morris Lane – Blue Run Road (CR54) in Jefferson Township at the 3.15 mile marker will be closed Tuesday,
May 10th from 7:00 A.M. to 5:00 P.M. The location of the closure is between Blue Run Road and Blue Run
Township Road. County Engineer’s crew will be installing a concrete pipe.
Great Meadow Road (CR51) in Bloom Township at the 2.85 mile marker will be closed Tuesday, May 10th from
7:00 A.M. to 5:00 P.M. The location of the closure is between Martin Road and Webster Hope Road. County
Engineer’s crew will be installing a concrete pipe.
Great Meadow Road (CR51) in Bloom Township at the 2.26 mile marker will be closed Wednesday, May 11th
from 7:00 A.M. to 5:00 P.M. The location of the closure is between Martin Road and Webster Hope Road.
County Engineer’s crew will be installing a concrete pipe.
Great Meadow Road (CR51) in Bloom Township at the 4.09 mile marker will be closed Wednesday, May, 11th
and Thursday, May 12th day and night. The location of the closure is between Webster Hope Road and Lick Run– Lyra Bloomswitch Road. County Engineer’s crew will be installing a concrete pipe.
Great Meadow Road (CR51) in Bloom Township at the 0.71 mile marker will be closed Thursday, May 12th from 7:00 A.M. to 5:00 P.M. The location of the closure is between Martin Road and State Route 140. County
Engineer’s crew will be installing a concrete pipe.
BRIDGE REPLACEMENT
Mackletree Road (TR99) in Nile Township at the 4.81 mile marker will be closed Monday, May 9th through
Friday, November 4th day and night. The location of the closure is between State Route 125 and the Shawnee
State Park shelter house. Sunesis Construction will be replacing a bridge.
LANE RESTRICTIONS
Fairground Road (CR55) in Valley Township continues to have lane restrictions through Saturday, May 14th from 7:00 A.M. to 6:00 P.M. each day. The Portsmouth Joint Venture implemented flagging operations to divert
traffic through a single lane to allow MSE (Mechanically Stabilized Earth) wall construction on bridges 15, 16
and 17. Wall construction will alternate between the east and west side of Fairground Road. A minimum of one
lane will remain open during construction hours. Both lanes will be open during the remainder of the day.
MOWING
Gephart Road in Bloom and Harrison Townships.
Poplar Fork Road and Clinton Furnace Road in Vernon Township.
Haverhill – Ohio Furnace Road in Green Township.
Pollock Road in Rush and Union Townships.
Carey’s Run – Pond Creek Road in Rush, Union and Washington Townships.
Slab Run Road in Washington Township.
Thompson Hill Road in Brush Creek and Union Townships.
Visit us on the web at SciotoCountyEngineer.org